Question

In a level terrain, a vertical orebody of 20 m uniform width is worked by surface mining method. The density of the ore is 2.5 tonne/m3^3. The ultimate pit has a depth of 60 m, width of 20 m at pit bottom, and a pit slope of 45°. The overall stripping ratio for this condition in m3^3/tonne is ______.

NAT

Min: 1.2 Max: 1.2

Answer: 1.2