A 10 m thick coal block is excavated by a contractor at a cost of Rs. 40 per m³. The excavated area, measured in the mine plan, is found to be50 cm². If the mine plan has been drawn to a scale of 1:1000, the payment to be made to the contractor, in lakhs of Rs., is _____
Min: 20 Max: 20
Answer: 20