A mine is being developed by bord and pillar method with a gallery size of . The mine operates in 3 shifts per day and 6 faces are blasted per shift. The average pull per round of blast is and the bulk density of coal is . If the OMS is , then the average manpower deployed in the development section per shift is ______.
Min: 46 Max: 47
Answer: 46.5