Question

A mill concentrate, having 25% copper, is proposed to be sold at Rs. 1,25,000 per tonne. The grade of the deposit is 0.8% Cu and the overall cost of mining and milling is Rs. 2,520 per tonne of ore. At a recovery of 75%, the estimated profit, in Rs./tonne of concentrate, is ______.

NAT

Min: 19500 Max: 20500

Answer: 20000

Solutions